Tokamak Energy and +BE Model Superconducting Power Distribution for Data Centres

Tokamak Energy and The BE Company (+BE) have published a feasibility study that models replacing copper with high-temperature superconductors (HTS) in the power distribution of a 10 MW data centre. The study claims up to 90% lower power losses at busway level and up to 50% lower total cost of ownership (TCO), but the release does not publish its method and names no pilot, customer or tape supplier. It adds a UK magnet maker to a data-centre market where VEIR and LS Cable & System are already further along.

Tokamak Energy and +BE modelled a 10 MW data centre

On 29 April 2026 Tokamak Energy published the results of a feasibility study carried out with +BE, which it describes as specialists in data centre infrastructure. The study models a 10 MW data centre in which rare-earth barium copper oxide (REBCO) superconductors replace copper in the power distribution system. The two companies were due to present the results jointly at the Open Compute Project’s Europe, Middle East and Africa summit in Barcelona on 29 and 30 April.

Tokamak Energy is a UK fusion company. Its HTS technology business, TE Magnetics, whose director is quoted in the release, sells superconducting technology for fusion, power systems, research and transport. Earlier in April, UK Fusion Energy named Tokamak Energy as Magnet Systems Partner for the STEP fusion programme under a £70 million contract running to March 2029.

The headline figures are modelled claims, mostly upper bounds

The release gives these results for the 10 MW case:

  • up to 3.5 times higher power density
  • up to 90% lower power losses at busway level (the enclosed conductors that carry power along rows of server racks)
  • system efficiency rising from around 90% to 99%
  • up to 50% lower TCO over a 15-year operating life
  • up to 9% more information technology (IT) capacity
  • up to 90% lower carbon dioxide (CO₂) emissions
  • up to 98% of the copper displaced
  • “millions of litres” of water saved, with no figure given

The release says the study covered cryogenic system requirements, thermal management, scalability, deployment timelines and TCO. It does not publish the method, the assumptions behind the cost and emissions figures, the authors or who paid for the work. Each number above is the study’s own claim and cannot yet be checked. Sath Ganesarajah, chief executive of +BE, said the conductors offer “a step-change in current density, losses, and footprint.” Liam Brennan, Director of TE Magnetics, called HTS a critical technology for UK energy resilience.

No installation, customer or supplier is attached

The announcement is a design study. It names no pilot site, data-centre operator, delivery date or order, and no conductor supplier or quantity of superconductor.

VEIR and LS Cable are further along in the same market

Other HTS hardware makers are already chasing data-centre power. VEIR delivered 3 MW through a single low-voltage superconducting cable in a simulated data centre in November 2025 and said it planned pilots in working data centres during 2026. Its system feeds server racks inside the building, the same level as the busway in this study.

In South Korea, LS Cable & System, LS Electric and Korea Electric Power Corporation signed a memorandum of understanding in July 2025 to build a superconducting grid for a data centre, which reports place at Gapyeong with completion targeted for 2028. That project works at the site supply level, at 23 kV. VEIR has run a demonstration and LS Cable has a utility partner and a reported site; the Tokamak Energy and +BE work has reached neither stage.

A pilot, a customer and a supplier would turn the study into tape demand

For tape producers, the study matters only if it leads to hardware. Three disclosures would mark that step: a pilot installation in an operating data centre, a named operator committing to buy, and a named tape supplier with a volume. Published TCO assumptions would also let operators test the 50% saving against copper busway. Until then, the 98% copper displacement figure describes a design on paper.

← All news