SWM and NKT Sign a Letter of Intent to Take SuperLink Commercial
Stadtwerke München (SWM), Munich’s municipal utility, and the cable maker NKT have signed a letter of intent (LoI) to take SuperLink, a high-temperature superconducting (HTS) power cable, from its test system toward a commercial contract. The LoI is not itself a contract: the two companies are still negotiating a binding agreement, and the release gives no timeline, value or tape supplier. A link of up to 15 km would be a sizeable tape order for whichever producer is chosen.
The letter of intent commits both sides to negotiate, not to build
On 15 April 2026 SWM and NKT signed the LoI to continue SuperLink. SWM says the aim is to create the conditions for a commercial contract, and that the two companies will now continue negotiations with the goal of concluding a binding one. Until that contract is signed, neither side has an order to book.
The release names no contract value, construction start, completion date or tape supplier, and no partners beyond the two companies. Helge-Uve Braun, SWM’s technical managing director, calls SuperLink a unique path in high-voltage cable technology that makes the grid more resilient and climate-compatible. Anders Jensen, NKT’s chief technology officer, says the LoI brings NKT much closer to a commercial contract.
The planned link would carry 500 MW over up to 15 km of central Munich
According to the LoI release, the commercial SuperLink would be a 110 kV connection up to 15 km long, carrying 500 MW through a particularly narrow urban corridor in central Munich. SWM describes it as the planned world’s longest superconducting high-voltage connection. The HTS cable is cooled with liquid nitrogen to about −200 °C, which the release says largely eliminates electrical losses.
SWM presents the cable as a response to grid bottlenecks in the city. The release says the compact design reduces civil engineering work and that redundant components raise reliability and operational safety. It gives no route, substations or cost.
The utility is moving from a test rig toward procurement
SuperLink is not starting from scratch. In October 2024 NKT and Stadtwerke München Infrastruktur energised a prototype test system at the Menzing main substation in Munich, with tape from the German producer THEVA. NKT said at the time that testing would run through the second quarter of 2025. The LoI release states that the test system has operated successfully and that the next step is a commercial version.
This is the point where a municipal utility stops hosting a trial and starts negotiating to buy. A binding contract would turn SuperLink from a demonstration into a procurement commitment, but the LoI on its own does not do that.
The tape supplier for the commercial cable is still open
A cable up to 15 km long would need a substantial quantity of superconducting tape. The release does not say how much, and it does not name a supplier. THEVA, which supplied the prototype, makes rare-earth barium copper oxide (REBCO) tape at Ismaning near Munich. It was acquired in April 2026 by Subra, a group that plans an integrated European HTS business running from REBCO coatings to complete cable systems.
That change of ownership matters for the commercial contract. The prototype’s tape came from an independent producer. THEVA now sits inside a group that also aims to supply cable systems, while NKT is the cable maker on SuperLink. For tape producers, the item to watch is whether the binding contract names THEVA, another supplier, or several. SuperLink is listed in our project table.